Framing lumber prices have dropped over the past month. If you are building or remodeling in the US with a framing package priced a few weeks ago, here is when lower prices actually reach you, how to ask for a re-quote, and how to keep your contract fair in both directions.

Last updated 16 November 2026. Prices from Madison's Lumber Prices Index and NAHB.

Not financial or legal advice. Read your own contract and quotes, and speak to an attorney before you change contract terms.

Where lumber prices are

  • Madison's Lumber Prices Index was $444 per thousand board feet for the week ending 13 November 2026, down 1% ($5) from $449 the week before and down 10% ($51) from $495 a month earlier.
  • NAHB reported the index at $459.10 as of 30 October 2026, down 4.4% year over year.
  • NAHB notes that the average new single-family home uses roughly 15,000 board feet of framing lumber, plus plywood and OSB.

These are mill-level index prices, not what your yard or framer charges, and they move week to week. We don't forecast where they go next.

Sources: Madison's Lumber Prices Index, 13 November 2026 · NAHB — Framing Lumber Prices

When falling prices actually reach you

NAHB says homebuilders and remodelers begin to get price relief once mill prices have fallen substantially for an extended period and/or stabilized, and that large drops alone may not be enough. Depending on how fast and how consistently prices fall, it may take at least a few weeks to a couple of months for builders to see the relief reported in futures or cash markets.

How long you wait depends on the size of your builder, the size of the supplier and the relationship between them. NAHB also points out that rising prices tend to reach builders much faster than falling ones. So a framing package priced in October may still reflect older, higher costs.

Lumber is down, but other inputs are up

A lower lumber price may not lower the whole bid. NAHB's analysis of the October 2026 Producer Price Index (published 13 November 2026) shows other inputs to a new home still rising:

  • Inputs to new residential construction, goods and services combined, were up 10.4% on a year earlier.
  • Building materials were up 5.8% on the year.
  • No. 2 diesel fuel was up 115.2% on the year, even after falling 4.6% in October.
  • Trade services were up 13.2% on the year.
  • Transportation and warehousing services were up 24.6%.

Fuel, transport and distribution costs sit in the same bid as the lumber. When you ask for a re-quote, ask which lines changed and why, so a lower lumber line isn't lost in rises elsewhere.

Source: NAHB Eye on Housing — Building Material Price Inflation Remains High Despite Energy Price Declines (13 November 2026)

How to ask for a re-quote

  • Start with what isn't ordered yet. Lumber that is already bought or delivered is unlikely to be repriced. Ask about packages still to be ordered.
  • Ask when the quote was priced. And ask whether the lumber lines are priced on current cost or on stock bought earlier.
  • Ask for the lumber separately.If lumber is buried in a framing sub's lump sum, ask for it as its own line so you can compare like for like.
  • Compare complete quotes. Check that a lower re-quote covers the same scope, grades and delivery. Our guide to comparing quotes covers what to check.
  • Be reasonable.If you have accepted a fixed price, your framer or supplier doesn't have to lower it unless the contract says so.

Escalation clauses that work both ways

An escalation clause lets the price rise if a named material cost goes up. If your contract has one, ask for a matching de-escalation term so the price can also come down when that cost falls. Make both directions use the same:

  • named index or price source,
  • base date and base price,
  • threshold before any change applies, and
  • list of materials covered.

Our fixed-price contract guide covers caps and time limits on escalation, and our Canadian lumber duty guide covers how to carry framing lumber in a budget.

Quote validity dates

Every lumber quote should say how long it is valid for. When a quote lapses, the price can be reset in either direction, so note the date and ask for a fresh price close to delivery.

Don't cut contingency on a short-term dip

Index prices move week to week, and lower mill prices take time to reach builders. Keep your contingency as it is until a lower price is in a signed quote or on a delivered invoice.

Keeping track of quotes

Record the validity date on the quote in ConstructionPro.io and note any price terms, so you can see when it lapses.

FAQ

Lumber prices are down. Why hasn't my framing quote dropped?

NAHB says builders begin to get relief once mill prices have fallen substantially for an extended period or stabilized, and that it may take at least a few weeks to a couple of months to see it. Suppliers need time to work through stock bought at higher prices, and how fast relief arrives depends on builder size, supplier size and the relationship between them.

If lumber is cheaper, why might my whole bid not come down?

Lumber is only one input. NAHB's analysis of the October 2026 Producer Price Index puts inputs to new residential construction up 10.4% on a year earlier, with No. 2 diesel fuel up 115.2%, trade services up 13.2% and transportation and warehousing services up 24.6%. A lower lumber line can be offset by other costs in the same bid.

Can I ask for a re-quote on lumber?

Yes, you can ask, especially for lumber that hasn't been ordered or delivered yet. Ask which lines are priced on current market cost, and when the quote was priced. Your framer or supplier doesn't have to lower a quote you have already accepted unless your contract says so.

What is a de-escalation clause?

It's the other half of an escalation clause: if the contract lets the price go up when a named material index rises, a de-escalation term lets it come down when that index falls, using the same index, base date and threshold. Ask for both directions if you agree to any escalation clause.

Should I cut my contingency now lumber is cheaper?

Not on a short-term dip. Index prices move week to week, and lower mill prices take time to reach builders. Keep your contingency until a lower price is in a signed quote or on a delivered invoice.

Does ConstructionPro.io track lumber prices or send re-quote alerts?

No. Record the validity date on the quote in ConstructionPro.io and note any price terms, so you can see when it lapses. The app doesn't track market prices or send alerts.